more on ORCL Oracle has notified the project developer — a subsidiary of Blue Owl Capital — invoking a force majeure clause to avoid substantial costs tied to its large New Mexico data-center, people familiar with the matter said. The notice seeks to defer payments if Project Jupiter is delayed and fails to go live as planned in 2028; the sources said Oracle is not seeking to exit as the anchor tenant. The move adds uncertainty to a project already facing local opposition and regulatory hurdles.